Mariko has created a work breakdown structure diagram to show work broken down into manageable pieces. Which choice is not a reason for creating the WBS?
1) To define the scope of the project
2) To allocate resources and estimate costs
3) To create a timeline for project completion
4) To identify potential risks and develop mitigation strategies
5) To track progress and monitor project performance