A project is set to be completed in 12 months with an estimated budget cost of $520,000. 6 months have passed, and expenses were $240,000. The completion of work is set to be $270,000
What is the planned value PV of the project?
What is the actual cost AC of the project?
What is the earned value EV of the project?
Find the SPI and CPI of the project.
Is the project ahead or behind schedule?
Is the project under or over budget?
What is the estimated cost to complete the project?