Under the Prompt Payment clause, unless specifically prohibited by the contract, the contractor is entitled to payment for accepted partial deliveries of supplies or partial performance of services that comply with all applicable contract requirements and for which prices can be calculated from the contract terms. What is the entitlement of the contractor under the Prompt Payment clause?
1) Payment for accepted partial deliveries of supplies
2) Payment for partial performance of services
3) Payment for supplies and services that comply with contract requirements
4) Payment for supplies and services with calculated prices