Tasha manages an applications migration project. The project requires managing teams handling various technologies. She needs to present project updates to the leadership team every Friday evening. She’s asked all the teams working on the project to send in their status reports by the end of Thursday, every week. It’s Friday morning and she has not yet received the Database team’s report. When she checks with them, they inform her that they had to handle a high-priority issue and have not worked on the status report. Which would be a good problem statement to describe Tasha’s problem?