If BAC is $ 85,000, Duration is 75 days, PV is $ 21,000, AC is $ 20,000, and % Complete is 27 %, what is the state of the project?
a. Under budget, behind schedule
b. Over budget, ahead of schedule
c. Under budget, ahead of schedule
d. Over budget, behind schedule