Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule.
Activity
Predecessor
Normal Time
Normal Cost
Crash Time
Crash Cost
Crash Cost Per day
A
-
12
200
9
350
B
A
8
300
6
300
C
A
9
250
7
450
D
B
6
400
5
600
E
B,C
5
150
4
225
F
C
10
500
9
650
G
D,E,F
8
400
6
900
Requirements (if not met will result in Zero credit)
Turn in the Word or Excel file.
Show the network diagram with all the values (ES, EF, LS, LF, slack, critical path).
Show all the computations in a sequential manner.
If you hand draw the network diagram, then include a legible snapshot in the Word or Excel file.