Urgent Math Help Needed Please!!!!
Table attached Below

The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B.

Question 2 options:

11 days


14 days


9 days


8 days

Urgent Math Help Needed Please Table attached Below The table shows five activities in days for a project Use PERT Program Evaluation and Review Technique to ca class=

Respuesta :

PERT = [tex]\frac{OT+4MLT+PT}{6}[/tex]

Activity B: OT = 3, MLT = 6, PT = 12

PERT = [tex]\frac{3+4(6)+12}{6}[/tex]

         = [tex]\frac{3+24+12}{6}[/tex]

         = [tex]\frac{39}{6}[/tex]

         = 6.5