Which employee's path is the critical path on this activity graph? Explain how you know that this employee's path is the critical path.

Which employees path is the critical path on this activity graph Explain how you know that this employees path is the critical path class=

Respuesta :

Answer:

Jim's path is the critical path on this activity graph.

Step-by-step explanation:

Critical Path:

Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.

In given case:

Path 1 Bill task's total duration= 6 days

Path 2 Jim's task's total duration= 17 days

Path 3 Betty task's total duration= 7 days

Path 4 Cynthia task's total duration= 14 days

Hence the longest path i.e. critical path is of Jim's activity path !