Answer:
The correct answer is C.
Explanation:
Giving the following information:
Costs associated with the alternatives are listed below.
Alternative X
Materials costs $ 41,000
Processing costs $ 45,000
Equipment rental $ 17,000
Occupancy costs $ 16,000
Alternative Y
Materials costs $ 59,000
Processing costs $ 45,000
Equipment rental $ 17,000
Occupancy costs $ 24,000
Only Material Costs are relevant because they vary whether you chose Alternative X or Y. Processing costs are the same in both options.