Using the information below for Sundar Company; determine the total manufacturing costs added during the current year: Direct materials used $20,300 Direct labor used 25,800 Factory overhead 48,600 Beginning work in process 12,000 Ending work in process 12,600 A) $94,700B) $46,100C) $94,100D) $45,500E) $73,800

Respuesta :

Answer:

The Answer is A

Explanation:

The Total Manufacturing cost is the sum of Direct Material used, Direct Material and Factory Overhead during the period.

Total Manufacturing Cost = $20,300 (Total Direct Materials used) + $25,800 (Direct Labour) + $48,600 (Factory Overheads)

Total Manufacturing Cost= $94,700  

 

Answer:The answer is C $94,100

Explanation:

To calculate the manufacturing cost

Direct Material + Direct Labour = Prime cost

20,300 + 25,800 = 46,100

The prime cost = $46,100

Then Add, Factory overhead and opening work in progress together and subtract it from closing work in progress

48,600 + 12,000 = 60,600

60,000 - 12,600 = 48,000

46,100 + 48,000 = 94,100

The total manufacturing cost =$94,100