The formula to the compute direct labor time variance is to calculate the difference between

a. (Actual Hours × Standard Rate) – Standard Costs
b. Actual Costs + Standard Costs
c. Actual Costs – (Actual Hours × Standard Rate)
d. Actual Costs – Standard Costs

Respuesta :

Answer:

The correct answer is A.

Explanation:

The general formula is:

Direct labor efficiency (time) variance= ( Actual Quantity - Standard Quantity)*standard rate

Note that none of the formulas provided matches the one I give you. But, with a small difference in the information, it can be adapted.

Direct labor efficiency (time) variance= Actual Quantity* Standard Rate - SQ* Standard Rate

If we are not provided with the Standard Quantity (SQ), but the total standard cost the formula is:

Direct labor efficiency (time) variance= (Actual Quantity* Standard Rate) - Standard cost

Therefore, the correct answer is A.