Strand Company is planning to sell 400 buckets and produce 380 buckets during March. Each bucket requires one-half hour of direct labor. Employees of the company are paid $15.00 per hour. How much is the total amount of budgeted direct labor for March?

Respuesta :

Answer:

total amount of budgeted direct labor = $2850

Explanation:

given data

sell  = 400 buckets

produce = 380 buckets

paid = $15.00 per hour

labor hour = 30 minutes

to find out

How much is the total amount of budgeted direct labor

solution

we consider labor rate is = $15 per hours

we get here total amount of budgeted direct labor that is express as

total amount of budgeted direct labor = produce × labor time × labor rate

total amount of budgeted direct labor = 380 × [tex]\frac{30}{60}[/tex] × 15

total amount of budgeted direct labor = $2850