Ed is managing a construction project. The function y = 0.75x represents the percentage of work done in terms of the number of weeks since the project started.

The values 0.75 represents ____.
The function representing the percentage of work that remains in terms of the number of weeks since the project started is y = ____ - ____x.

first blank:
A. the percentage if work done
B. the number of weeks since the work started
C. the percentage of work done every week

second blank:
A. 0
B. 0.75
C. 75
D. 100

third blank:
A. 75
B. 0.75
C. 0
D. 100

Respuesta :

Answer:

  • C, D, B

Step-by-step explanation:

Function given:

  • y = 0.75x

Where y - percentage of complete work, x - number of weeks, 0.75 - weekly completion rate

The values 0.75 represents the percentage of work done every week .

  • first blank:  C. the percentage of work done every week

The function representing the percentage of work that remains in terms of the number of weeks since the project started is y =100 - 0.75x

  • second blank:  D. 100
  • third blank:  B. 0.75