Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.5 day, and its average queue time is 3.0 days.
Required:
a) What is the Wait Time?
b) What is the Process Time?
c) What is the Inspection Time?
Round your answer to 1 decimal place.

Respuesta :

Answer:

Consider the following calculations

Explanation:

Answer a.

Delivery Cycle Time = 33.0 days

Throughput Time = 15.0 days

Delivery Cycle Time = Throughput Time + Wait Time

33.0 = 15.0 + Wait Time

Wait Time = 18.0 days

Answer b.

MCE = 0.32

Throughput Time = 15.0 days

MCE = Process Time / Throughput Time

0.32 = Process Time / 15.0

Process Time = 4.80 days

Answer c.

Throughput Time = Process Time + Inspection Time + Move Time + Queue Time

15.0 = 4.80 + Inspection Time + 0.4 + 7.0

Inspection Time = 2.8 days