Answer:
Option (b) is correct.
Explanation:
Given that,
Budgeted production (September) = 50,000
Direct labor time for producing each sneaker = 2 hours
Direct labor wages average = $15 per hour
Direct labor budget for September:
= Budgeted production of sneaker in September × direct labor time require for each sneaker × Direct labor wages average per hour
= 50,000 × 2 hour × $15
= $1,500,000
Therefore, the direct labor cost budgeted for September is $1,500,000.