In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more), and each time, the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.

Respuesta :

The given statement " In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more), and each time, the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager " is FALSE

Explanation:

Enumeration methods are used for solving combinational problems of optimisation. Combinatory optimization issues are difficulties where choices are binary, in which an object is selected or is not selected

(e.g. line, edge, node).

Basic schedule management strategies include starting and finishing dates for work in a project. Here the shadow bars stretch from the critical path-determined beginning date.

The Enumeration system includes census administration, handling money, computer awareness, Web surveying, information on housing records, post-enumeration analysis and web-based input and distribution of field information.