Answer:
The correct answer is letter "B": Escalating commitment.
Explanation:
Escalating commitment implies adding more resources to a project that is failing. The reason why more resources are added is that the individuals in charge of the project do not want to make it look inconsistent. Those resources are diverse and include capital, labor or raw materials.