Answer:
13 painters
Total number of painters needed N = NI + Ns
N = 6 + 7 = 13 painters
Step-by-step explanation:
Given:
Each painter can paint 2 large murals per day
OR
7 small murals per day.
In 2 days;
Each painter can paint 2×2 = 4 large murals
OR
7×2= 14 small murals
The number of painter needed to paint 24 large murals and 98 small murals in two days.
For the large murals
Number of paiters needed for the large murals Nl = total number of large murals to be painted in two days/number of large murals each painter can paint in two days
NI = 24/4 = 6 painters
For the small murals
Number of painters needed for the small murals Ns = 98/14 = 7 painters
Total number of painters needed N = NI + Ns
N = 6 + 7 = 13 painters