Answer:
C. Resource limited scheduling
Explanation:
Resource limited scheduling is a method for developing the shortest schedule when the number or amount of available resources is fixed. It is a project schedule which defines that when when activities are going to start, their finish dates and directly reflects and manifests the availability of all the resources needed for that project. This method is most appropriate when the resources for the project are scarce and limited and those resources can not be exceeded in any case.