Answer:
Option B It presents variable cost as a slope coefficient
Explanation:
The reason is that the total cost function is:
Y = a + bx
The total cost in this case is Y, a is fixed cost as an intercept, b is variable cost represented as an slope and coefficient and x is level of activity which is independent of Y.