Answer:
$166.8
Explanation:
Given that,
Units expected to produced = 400,000 units
Machine hours required = 1.2 each
Manufacturing overhead costs:
= Department 1 + Department 2
= $2,530,000 + $2,752,000
= $5,282,000
Total Machine hours:
= Department 1 + Department 2
= 30,000 MH + 8,000 MH
= 38,000 MH
Overhead cost per machine hour:
= Manufacturing overhead costs ÷ Total Machine hours
= $5,282,000 ÷ 38,000 MH
= $139 per MH
Overhead cost per unit:
= Overhead cost per machine hour × Machine hours required for each
= $139 per MH × 1.2
= $166.8