Ralph is estimating the cost of concrete to build a slab. The slab will have a length of 12 feet, a width of 9 feet, and a thickness of 6 inches.
He will order 10% extra concrete to allow for spillage. The cost of concrete is $85 per cubic yard. How much does Ralph need to spend on
concrete for the job?

Respuesta :

Answer:

The actual answer is 187 dollars

Step-by-step explanation:

Volume is a three-dimensional scalar quantity. The cost Ralph needs to spend on concrete for the job to be done is $187.

What is volume?

The amount of three-dimensional space enclosed by a closed surface is expressed as a scalar quantity called volume.

The volume of the concrete that will be needed for the slab with a length of 12 feet, a width of 9 feet, and a thickness of 6 inches(1/2 feet). can be written as

[tex]\rm \text{Volume of Concrete} = Length \times Width \times Thickness[/tex]

                               [tex]\rm = 12 \times 9 \times \dfrac12\\\\=54\ ft^3[/tex]

As it is given that 10% extra concrete is needed for the spillage. Therefore, the volume of concrete that will be needed is,

[tex]\rm Concrete\ Needed= 54 (100\%+10\%) = 54(110\%) = 59.4\ ft^3[/tex]

Now the volume of the concrete in yds³ can be written as,

[tex]\rm Concrete\ Needed= 59.4\ ft^3 = \dfrac{59.4}{27} = 2.2\ yds^3[/tex]

As it is known that the cost of concrete is $85 per cubic yard, therefore, the cost of the concrete can be written as,

[tex]\rm Total\ Cost = (Concrete\ Needed) \times \text{(Cost per cubic yard)}[/tex]

                   [tex]=2.2 \times \$85\\\\= \$187[/tex]

Thus, the cost Ralph needs to spend on concrete for the job to be done is $187.