Which of the following is NOT a role of the closure facilitator?a. Use several questionnaires as a starting point to conduct the post-project retrospectiveb. Get delivery acceptance from the customerc. Elicit a 360-degree view and input from all stakeholders to create a more complete picture of project issuesd. Lead the team in exploring new ways for solving problemse. Create an environment in which stakeholders feel safe to provide input

Respuesta :

Question options:

A. Create an environment in which stakeholders feel safe to provide input.b)Get delivery acceptance from the customer.c)Elicit a 360-degree view and input from all stakeholders to create a more complete picture of project issues.d)Use several questionnaires as a starting point to conduct the post-project retrospective.e)Lead the team in exploring new ways for solving problems

Answer:

b)Get delivery acceptance from the customer

Explanation:

The closure facilitator can be the project manager and does not get delivery acceptance from customer in project management. The closure facilitator is the one in charge of ensuring project objectives are met by drafting the agendas and looking for ways to achieve meeting objectives in project facilitation. The project facilitator creates an environment that makes it possible for the group and everyone involved in the project to put heads together to solve problems in the project