Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor: BCWS BCWP ACWP BAC EAC 7 6 6 10 10 Calculate the Cost Performance Index (CPI). Based on the CPI: a. The contractor has spent 85% of the budget. b. The contractor is on track to meet the Budget at Completion (BAC). c. The contractor will finish on time. d. The contractor seems inefficient in terms of cost.