Respuesta :
Answer:
the overhead cost assigned to Job 971 is $1,020
Explanation:
The computation of the overhead cost assigned to Job 971 is shown below:
= Budgeted Machine overhead cost ÷ Number of set up
= $13,200 ÷ 390
= 34
Now the overhead cost assigned is
= 30 setups × 34
= $1,020
hence, the overhead cost assigned to Job 971 is $1,020
Therefore the last option is correct
The overhead cost assigned to Job 971 is $1,020 by using the ABC method.
What is the calculation of overhead cost?
The overhead cost is derived after multiplying the machine setup of Job 971 with the Budgeted machine setup cost.
Here, the budgeted machine setup cost would be;
[tex]\frac{ 13,260}{390} \\=34[/tex]
Thus, the overhead costs would be;
[tex]30*34\\=1020[/tex]
Learn more overhead costs here:
https://brainly.com/question/26511051