Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 367 minutes per day, excluding three 17-minute breaks, and an hour for lunch. The service system must process 97 jobs a day.

Respuesta :

Answer:

2.64 minutes per cycle

Explanation:

Total work time = 367 minutes per day

Break time = 17 min*3 = 51 min

Lunch time = 60 min

Total time left =  367 - 51 - 60 =  256 min

Demand = 97 jobs a day

Takt time = Total production time available/Demand

Takt time = 256 / 97

Takt time = 2.639175257731959

Takt time = 2.64 minutes per cycle