Respuesta :
Answer:
the manufacturing cycle efficiency (MCE) for Hunt Company is 25%
Explanation:
The computation of the manufacturing cycle efficiency is shown below:
We know that
MCE = Value-added time ÷ Throughput time
Here
Value-added time = Process time = 1 hour
And, the Throughput time = 4 hours
So,
MCE = 1 ÷ 4
= 25%
hence, the manufacturing cycle efficiency (MCE) for Hunt Company is 25%
The manufacturing cycle efficiency (MCE) for Hunt Company is: 25%.
Using this formula
Manufacturing cycle efficiency= Process time ÷ Throughput time×100
Where:
Process time =1 hour
Throughput time = 4 hours
Let plug in the formula
Manufacturing cycle efficiency= 1 ÷ 4×100
Manufacturing cycle efficiency= 25%
Inconclusion the manufacturing cycle efficiency (MCE) for Hunt Company is: 25%.
Learn more here:https://brainly.com/question/13065083