A-project-of-construction-of-a-building-can-be-completed-by-150-workers-in-40-days-But-project-manager-brought-30-more-workers-after-16-days-In-how-many-days-will-the-remaining-work-be-finished

Respuesta :

Answer:

In the second scenario after 16 days, 150 workers would have completed 150*16=2400 worker days. That leaves 6000-2400=3600 worker days remaining. If you add 30 workers, it would take 3600/180=20 days longer to complete. So, the entire project would take 16+20=36 days to complete.