The economic order quantity is 385 and reorder point is 254.
a. Economic order quantity (EOQ)
EOQ=√2×D×C÷H
Where:
D =Annual Demand
S = Cost of Ordering
H=Holding cost
Hence:
EOQ=√2×5300×70÷.25×20
EOQ=√742,000÷5
EOQ=√148,400
EOQ=385
b. Reorder point
Reorder point=5300/250×12 days
Reorder point=254
c. Reorder point
Reorder point=5300/250×35 days
Reorder point=742
d. Reorder point
Reorder point=742-385
Reorder point=357
Therefore the economic order quantity is 385 and Reorder point is 254.
Learn more about Economic order quantity (EOQ) here:https://brainly.com/question/16024963
#SPJ1
The complete question is:
a. If the cost of the part is $20 per unit, what is the economic order quantity?
b. Assume 250 days of operation per year. If the lead time for an order is 12 days, what
is the reorder point?
c. If the lead time for the part is seven weeks (35 days), what is the reorder point?
d. What is the reorder point for part (c) if the reorder point is expressed in terms of the inventory on hand rather than the inventory position?