schedule constraints would usually include all of the following except: a. imposed dates b. key events c. major milestones d. lead times and lag times

Respuesta :

Schedule constraints would never include leads and lags.

Due to scheduling restrictions, activities would not have leads and lags. It would make sense to include schedule constraints for items A, B, and C.

A schedule constraint is a precise restriction imposed on a project schedule to control when a task or activity can begin or end. In order to prohibit some activities from beginning too soon (an activity should not begin earlier than a specified date) or ending too late, schedule constraints are used to set boundaries on work items (restriction on delay).

This occurs because certain activities may not be permitted for a planning procedure that could assign these things to multiple dates; instead, they should be bound to set dates.

Learn more about schedule constraint here:

https://brainly.com/question/28282853