the following information is given for a cpm network: activity predecessor successor normal time normal cost crash time crash cost a --- b, c 5 $ 60 2 $ 125 b a d, c 4 70 2 90 c a, b d 6 80 3 150 d b, c --- 3 40 1 60 what is the project cost if the project is crashed by one day? multiple choice $125 $250 $270 none of these choices are correct.

Respuesta :

The following information is given for a Cpm network: activity predecessor successor normal time normal cost crash time crash cost:

A - C - D .

What exactly is a CPM network?

The least reliable method for predicting how long a project will take is the sequence of activities. It is founded on an assessment of the typical amount of time required to complete a task. The project's time and budget are managed by CPM.

With this approach, the project's critical path is formed by determining which project tasks are most important. The critical actions are those with a total float value of '0'.

To know more about cpm network, visit:

https://brainly.com/question/14739113