CP and PERT do NOT perform well in projects where the Customer market is stable. The end goal is not clear. The time elapsed is short. The competition is understood. The technology is mature. What is the reason for their poor performance in such projects?
1) The project requires a flexible approach
2) The project requires a clear and well-defined goal
3) The project requires a longer time frame
4) The project requires a better understanding of the competition