Use the process information provided in the following table, when the sequence of flow is A → B (any machine can be used if available) → C → D (any machine can be used if available).

Operation Number of Units of Equipment Design Capacity (by equipment) Planned Utilization (overall)
A 1 300 units per hour 76.0%
B 4 70, 60, 100, 50 82.5%
C 1 310 units per hour 67.0%
D 2 200, 75 85.0%
Calculate the maximum (design) capacity and effective capacity.