The project currently has Positive 5 days slack.
Times needed for task A = 7 days
Times needed for task B = 5 days
Times needed for task C = 8 days
Total predicted days = 20 days
Since the project is required to be completed in 25 days, the company has 25 days - 20 days = 5 days positive