Answer and Explanation:
the computation is shown below:
1. Setup Time standard
Here the first quarter standard would be considered i.e. 9 hours so we dont take the actual setup time
The Second quarter is 1 hour that denotes the Expected setup time
2. The Total non-value cost which got eliminated is
Since, The setup time was Decrease from 12 hours to 3 hours.
So, the Total non value added cost eliminated is
= $600 × (12 - 3)
= $600 × 9
= $5,400